Now we are moving along, the first floor frame is mostly complete.The trickyest part of the whole frame stage, cutting into the old roof (over two existing rooms) and running LVL`s from front to back has been done sub-floor inspection passed and flooring down with some walls going up. Should be ready for a roof by the end of this week!
latest update is the roof is on and most of the flashings so we can start to clad the walls- Hebel panels are going on the walls, not the lightest things to lift
sparkies has with my able assistance started the rough in downstairs.
air con has been roughed in
as has the hydronic heating
next major thing is the windows and doors which are on order
frame inspection passed without a hitch
anyway some pics for you all
looks awesome, esp the fact that there is a beer bottle visiable in most of the photos! Damn good work site! Don't forget to wire for pay tv / sound / networking / FreeTA..
does scaffold in picture 2 conform to w.h.&s rule's
"owner builder rules" OK
Good bit of work! Reckon I would have been using more insulation eg: Insulboard styrofoam and some internal ply bracing rather than the ply, but less a problem in a terrace, but gunna be a nice place though!
__________________ Advice from me on this forum is general and for guidance based on information given by the member posing the question. Not to be used in place of professional advice from people appropriately qualified in the relevant field. All structural work must be approved and constructed to the BCA or other relevant standards by suitably licensed persons. The person doing the work and reading my advice accepts responsibility for ensuring the work done accords with the applicable law.