Quote:
Originally Posted by Jessie The company doing renovation for us has just put wrong tiles onto our bathroom (It's different from specified in the contract). I don't want them to re-work because it will take another 2-3 months. I'm seeking for a compensation. |
Who made the mistake? The right amount of compensation is the cost to that person (or persons) of putting it right. That's what it would cost the renovation company - if it is not the builder's mistake, it might cost him nothing.
Worst case for the builder is cost of correct tiles + cost of installation + cost of demolition. Best case for them is either the tiler fixes it for nothing or you get zero compensation.
Of course the builder might insist on putting in right, in which case there's no compensation payable, except if your bathroom is out of use for an extra 3 months, it would be reasonable to get compensation for that. If it is going to take more than 1 week extra, I'd demand compensation and I'm sure the builder will get it done faster than 2-3 months.
Get the agreement about rework and time frame and compensation for lateness in writing. If you agree on the phone, then write/fax a letter to him confirming the discussion and the agreement you reached.