    This was not my mistake but I needed to fix the problem.

    We bought this place to live in while we build the Belair house and although I knew there were a few loose tiles in the shower a bigger problem was waiting to be discovered.

    When the original wall lining was nailed in place a nail had been driven into the pipe between the breaching piece and the shower head. The resulting leak caused all the timber stud work to rot away. This didn't happen straight away of course, the nail blocked the hole for a long time, until it eventually corroded away. The leak only happened while the shower was in use and any water found its way back into the shower so it was never detected by the previous owner.

    bathroom.jpg

    bathroom2.jpg

  2. #2
    chalkyt is offline Senior Member
    Join Date
    Sep 2010
    Location
    Jindabyne
    Posts
    451

    Default

    Yes, I found something like that in a place we renovated. Nice black crumbly wood all being held up by the roof! What fun!!!!

  3. #3
    ringtail is offline 3K Club Member
    Join Date
    Sep 2009
    Location
    brisbane
    Posts
    3,001

    Default

    At least the asbestos is still good . Get the plumber to solder in new pipe work as close to that wall junction as possible, then run a new stud up each side of the existing, a few new nogs, resheet and tile. I'd probably get a heat gun or similar onto those studs where the damage is the worst and try to dry them out a bit first

  4. #4
    Belair_Boy's Avatar
    Belair_Boy is offline Owner Builder
    Join Date
    Nov 2010
    Location
    Belair South Australia
    Posts
    347

    Default The repairs

    This was all about 4 years ago.
    I ended up replacing the lining behind the tiles on all 4 walls in the bathroom while I was at it.
    Rotten stud work behind the shower just crumbled away so just vacuumed up and replaced with fresh, new bottom plate as well.
    New ceiling, with insulation, a roof ventilator, extractor fan/heat light, new vanity, mirror, much filling and sanding, plus a new coat of paint and the bathroom should last us while we are living here at least.

    bathroom3.jpg

    bathroom4.jpg

  5. #5
    GeoffW1 is offline GeoffW1
    Join Date
    Jul 2008
    Location
    Sydney Australia
    Age
    66
    Posts
    471

    Default

    I drilled through a pipe I'd only just put in there LOL

  6. #6
    nataliejw81 is offline Apprentice (new member)
    Join Date
    May 2012
    Location
    sydney
    Posts
    8

    Default

    my husband tiled the bathroom in our old house but decided to do it the hard way and start from the roof down, using nails to hold up each run as he glued them on ... went straight through the hot water pipe!! what luck!

Similar Threads

  1. I think we may have made a small mistake
    By Moondog55 in forum STRUCTURAL RENOVATION
    Replies: 21
    Last Post: 4th May 2011, 04:00 PM
  2. Spot the mistake
    By Moondog55 in forum AT THE END OF THE DAY
    Replies: 6
    Last Post: 22nd Oct 2010, 08:53 PM
  3. Deck Sealing - Big Mistake
    By LotteBum in forum DECKING
    Replies: 4
    Last Post: 1st May 2008, 12:02 PM
  4. Mistake in Link
    By pawnhead in forum FORUMS INFO, HELP, DISCUSSION & FEEDBACK
    Replies: 1
    Last Post: 10th Jan 2007, 07:33 PM
  5. Help Floor Joists-Stupid mistake made
    By pantotango in forum SUB FLOORING
    Replies: 3
    Last Post: 18th Mar 2006, 06:49 PM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •