Hire the best Concreting Expert

Settling of fill under new garage slab: necessary?

Results 1 to 13 of 13
  1. #1
    Senior Member
    Join Date
    Nov 2007
    Location
    Cairns
    Posts
    146

    Default Settling of fill under new garage slab: necessary?

    Hi

    I want to build a colourbond double garage next to my house. The house was built (40 years ago) on a raised platform of fill. My father suggested I get fill put in next to the house to enable the garage to be level with the house (instead of about 4 feet below). Sounds like a great idea to me. Will I need to wait for the fill to settle before laying the slab? I know there won't be a great deal of weight on it but I'd like to sure before I start proceedings.

    Many thanks in advance.
    Brett

  2. #2
    Registered User
    Join Date
    Nov 2007
    Location
    Orstralia
    Posts
    259

    Default

    Hire a vibrating compacting plate and do the job properly.
    Put down a 150mm layer, compact, repeat, repeat, etc, etc.

  3. #3
    Diamond Member Terrian's Avatar
    Join Date
    Nov 2005
    Location
    Kilsyth, Victoria
    Age
    64
    Posts
    1,065

    Default

    about 8 years ago we filled an area, mostly clay fill, to a depth of about 1.2m, over 5 or 6 years it settled down about 150mm, mind you, we did not use a compactor at all, though I did spread it with a bob cat, does that give you an idea.

  4. #4
    1K Club Member journeyman Mick's Avatar
    Join Date
    May 2003
    Location
    Kuranda, paradise, North Qld
    Age
    61
    Posts
    1,782

    Default

    If you're going to prepare a platform 1200 high and big enough for a double garage you'll be looking at a lot of fill. Filling to that depth and with that amount of fill you'll need at least a bobcat to spread the fill and a vibrating pedestrian roller to compact. You'll also need to scalp all the topsoil off the site beforehand.

    Mick
    "If you need a machine today and don't buy it,

    tomorrow you will have paid for it and not have it."

    - Henry Ford 1938

  5. #5
    Senior Member
    Join Date
    Nov 2007
    Location
    Cairns
    Posts
    146

    Default thanks

    Thanks a lot for your input. I have a much better idea of what's required now. Cheers, Brett

  6. #6
    Senior Member
    Join Date
    Feb 2006
    Location
    vic
    Posts
    181

    Default

    It would probably crack with normal reo with no internal beams if you drive a car on it.

  7. #7
    Member
    Join Date
    Jul 2004
    Location
    Singleton NSW
    Age
    68
    Posts
    70

    Default

    I filled an area to about 900mm for my 6M X 14M shed. It has sunk about 50 - 70 mm in a couple of places - Unfortunately a family of Red Belly Black Snakes have now moved into the gap

    woodcutta

  8. #8
    Diamond Member Terrian's Avatar
    Join Date
    Nov 2005
    Location
    Kilsyth, Victoria
    Age
    64
    Posts
    1,065

    Default

    Quote Originally Posted by woodcutta View Post
    I filled an area to about 900mm for my 6M X 14M shed. It has sunk about 50 - 70 mm in a couple of places -
    filled areas have a bad habit of doing that, even if you roller compact as you go.

    Unfortunately a family of Red Belly Black Snakes have now moved into the gap

    woodcutta
    look on the bright side..... ummmm, can't think of one at the moment, but 'always look on the bright side of lie, da dum, da dum dum dum dum'

  9. #9
    Landscaper Planned LScape's Avatar
    Join Date
    May 2007
    Location
    Bundoora, Melbourne
    Posts
    340

    Default

    What you could do is put your fill in and compact as well as possible, then get a machine in to drill some holes into solid ground beneath the fill area, then fill with concrete to act as piers to hold up your slab.
    Planned Landscape Constructions

  10. #10
    Member
    Join Date
    Jul 2004
    Location
    Singleton NSW
    Age
    68
    Posts
    70

    Default

    [quote=
    look on the bright side..... ummmm, can't think of one at the moment, but 'always look on the bright side of lie, da dum, da dum dum dum dum'[/quote]


    Maybe they sleep in the winter??

    woodcutta

  11. #11
    A Member of the Holy Trinity silentC's Avatar
    Join Date
    Aug 2003
    Location
    Pambula
    Age
    57
    Posts
    2,714

    Default

    One part of our house sits on an infill slab. It has brick piers every metre with extra reo over the piers (as specified by the engineer). It is back filled with sand, which does not compress - however it only needs to act as formwork for the slab pour because the piers will take the weight. The piers are founded in solid ground with a 600x600x600 footing under each. The perimeter of the slab sits on continuous brickwork which is laid on a strip footing. There is a slip joint between the slab and the brickwork.
    "I don't practice what I preach because I'm not the kind of person I'm preaching to."

  12. #12
    Senior Member Rossluck's Avatar
    Join Date
    Dec 2005
    Location
    Gold Coast
    Age
    65
    Posts
    105

    Default

    4 foot is a decent depth to fill, Brett. Not something I'd take too lightly. The idea of dumping fill in there and compacting it doesn't work for me. It will settle over time and cause problems.

    In fact, I don't think I'd tackle it myself because it sounds like it needs:

    * Something to retain the fill, i.e, retaining walls
    * Piers into solid ground
    * Crusher dust or sand (non-compacting fill)
    * Then the slab (that sits on the piers.

    But most of all, you need a soil test and an engineer. I'd be very surprised if the council will let you do anything other than have an engineer look at it if you want to raise it four feet. Silent's post outlines the way it needs to be done.

  13. #13
    Senior Member
    Join Date
    Nov 2007
    Location
    Cairns
    Posts
    146

    Default

    Thanks for all the advice. I knew what to expect when I called the garage people who put me on to the concreter. He said it wouldn't be a drama - he'd put piles down to hard ground and lay the slab on top. No big deal (it would cost a bit more of course, but that was to be expected). He did make the good suggestion that I step the garage down, ie only half the fill-height, so the buildings flowed more with the block. Sound idea. Thanks again everyone. It's amazing how quickly you can go from knowing absolutely nothing to having a bit of an idea.

    cheers, Brett

Similar Threads

  1. Garage Slab
    By nev25 in forum Structural Renovation
    Replies: 7
    Last Post: 21st May 2008, 12:56 AM
  2. Estimate cost of garage slab please?
    By juliussee in forum Concreting
    Replies: 21
    Last Post: 17th Mar 2008, 06:35 PM
  3. garage slab engineering
    By Amb in forum Concreting
    Replies: 7
    Last Post: 23rd Jul 2007, 11:12 AM
  4. How to fill 30mm gap in slab.
    By martrix in forum Concreting
    Replies: 17
    Last Post: 11th Feb 2007, 10:54 PM
  5. garage slab concrete - subbase
    By XT4V in forum Concreting
    Replies: 34
    Last Post: 1st May 2006, 06:39 AM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •