Connecting to the Grid in Sydney

Results 1 to 3 of 3
  1. #1
    Novice
    Join Date
    Oct 2009
    Location
    Merrylands, Sydney
    Posts
    20

    Default Connecting to the Grid in Sydney

    I had a 3kw solar system installed on my roof on May 20th 2011. My paper work for connection to the grid (sent to Endeavour Energy on 26th April) was not sent back to my solar company until 17th June 2011. I am still waiting to be connected. Endeavour Energy just told me that the electrician who was connecting me had been banned but was taken off the banned list on 5th July 2011. When I asked what this meant I was told he had reached his credit limit on meters. What does this mean? Can anyone enlighten me on why it is taking so long to connect? Do electricians know they are banned? I would appreciate any answers as I am still paying exorbitant electricity bills and there is $8,000 worth of solar panels on my roof not being used.

  2. #2
    Old Chippy 6K
    Join Date
    Mar 2007
    Location
    Canberra
    Age
    69
    Posts
    6,561

    Default

    A guess only, but it sounds like a simple case of a slow paying electrician. Seems he has an account with the utility to allow him to purchase up to a certain limit and he is over it, so credit stops until he pays off the account. If you have already paid your sparky (shouldn't have done until you had a live connection, but seems too late for that now . . .) then you need to harrass the sparky until he fixes the issue. Then again utilities are not renowned for great billing systems or customer service of course so who knows . . .
    Advice from me on this forum is general and for guidance based on information given by the member posing the question. Not to be used in place of professional advice from people appropriately qualified in the relevant field. All structural work must be approved and constructed to the BCA or other relevant standards by suitably licensed persons. The person doing the work and reading my advice accepts responsibility for ensuring the work done accords with the applicable law.

  3. #3
    Novice
    Join Date
    Oct 2009
    Location
    Merrylands, Sydney
    Posts
    20

    Default

    Thanks for that Bloss, but I did some further investigation of this. You are right he did reach his credit limit but that has now been fixed, the problem now is that Endeavour Energy does not have enough net meters. When the NSW government closed the scheme, Endeavour sat on all applications for over 4 weeks, now they say there is a further wait of 4 to 8 weeks because of the shortage of net meters. So I can get angry with Endeavour or with the government. I know I am not the only one in this situation but it seems to be there is a deliberate attempt to hurt the solar industry in this state. So I will sit in the cold and wait until I am connected. Thanks again.

Similar Threads

  1. Grid connect solar setup
    By Ausyuppy in forum Solar Electrical Systems
    Replies: 35
    Last Post: 8th May 2010, 10:34 PM
  2. Replies: 14
    Last Post: 29th May 2009, 05:46 PM
  3. Solar Grid-Connect: Noisy Inverter
    By Nifty1 in forum Electrical
    Replies: 4
    Last Post: 6th May 2009, 04:28 PM
  4. Solar grid connect
    By JackG in forum Solar Electrical Systems
    Replies: 15
    Last Post: 19th Oct 2007, 07:04 PM
  5. EZI-GRID TILEBACKER vs VILLABOARD
    By EXKIWI in forum Bathrooms
    Replies: 2
    Last Post: 1st Jan 2007, 11:59 AM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •