    Hi all,

    A couple of quick bond breaker questions which i've not managed to find answers too :


    I am about to waterproof a shower which has an 80mm recess into the concrete slab. My plan is to waterproof the recess which is part of the slab, then install the villaboard and screed then waterproof over the top and of course, fit bond breakers at the joints where the screed meets the villaboard (and internal wall corners as usual).

    Is it ok to not install bond breakers in the recessed slab as it is a single piece of concrete and the base cannot move seperately from the sides?

    Second question, i am having to install the villaboard horizontally due to the size of the shower, do i need to do anything special where the joint is from a waterproofing perspective, or if i tape and coat the joint as normal is it treated as a single sheet and just waterproofed?

    Thanks

    J

  2. #2
    Senior Member
    Join Date
    Mar 2016
    Location
    North East VIC
    Posts
    184

    Default

    If you waterproof on top of the screed you must wait for it to be fully dry AFTER correctly curing the screed first. Curing means keeping the screed damp. So it may mean delaying the job 20+ days depending on how thick the screed is.

    If you install the sheeting, water proof and then install the screed you can get on to tiling quicker if you choose to not water proof on top.

    First question, not sure but I would as you can use silicon in a 12mm bead as a bond breaker and then use normal bandage on top of silicon. If you sheet first you can do it all at the same time. Don't forget some wood in the areas you water to screw the glass to, wood for towel rails, toilet roll holder and hand rails for elderly that kind of thing before you sheet.

    This link may be of interest


    https://www.renovateforum.com/f205/s...nsuite-119419/

  3. #3
    Member
    Join Date
    Oct 2014
    Location
    Sunshine Coast
    Posts
    74

    Default

    Thanks Skinah, nice shower !

    At this stage i have decided to just WP below the screed and depending on how the next few days go I will review this decision.

    I have sheeted the two walls of the recess (which extends down into the recess 75mm) and used 11fc for all joints. Got a little carried away with the jointing beed but as i'm going to be using the fabric with built in bond breaker so i guess a little extra filling shouldn't matter too much.

    i'm still interested to understand whether a taped and filled horizontal board joint is considered two different surfaces which could move independently and therefore need a bond breaker. I was planning on reinforcing the joints with wp fabric but not the one with built in bond breaker.

    Cheers

    J

  4. #4
    Community Moderator phild01's Avatar
    Join Date
    Aug 2009
    Location
    Sydney, north
    Posts
    16,194

    Default

    Running your boards horizontal is fine, just don't topcoat the joins, no need for bond breaking. Also backblock the joins. Waterproofing the walls is way over-rated compared to the floor to wall requirement. I have pulled old showers apart with no wall waterproofing and with nil wall water damage. You need to waterproof the walls though, but just be sure the floor area and wall intersections are given close attention to bond breaking and manufacturer's application.

    A good guide to waterproofing thickness is to read what the manufacturer says about coverage. If you think you have applied enough but find you have used less than what is spec'd, then keep going with further coats.

  5. #5
    Member
    Join Date
    Oct 2014
    Location
    Sunshine Coast
    Posts
    74

    Default

    Quote Originally Posted by phild01 View Post
    Running your boards horizontal is fine, just don't topcoat the joins, no need for bond breaking. Also backblock the joins. Waterproofing the walls is way over-rated compared to the floor to wall requirement. I have pulled old showers apart with no wall waterproofing and with nil wall water damage. You need to waterproof the walls though, but just be sure the floor area and wall intersections are given close attention to bond breaking and manufacturer's application.

    A good guide to waterproofing thickness is to read what the manufacturer says about coverage. If you think you have applied enough but find you have used less than what is spec'd, then keep going with further coats.

    Thanks Phil,

    I've done waterproofing before using the same kit so i'm not too worried about getting the right coverage, I will probably do more than less - it was just more that last time the shower was small enough to use vertical boards without a join. In my mind the boards can in theory move independently at the join however probably not enough to be of consequence. The studs are 350 apart as well so quite a bit of support.

    J

  6. #6
    Community Moderator phild01's Avatar
    Join Date
    Aug 2009
    Location
    Sydney, north
    Posts
    16,194

    Default

    Backblocking is easy and the boards won't move. Villaboard joins must be supported by either noggins or backblocking.

  7. #7
    Member
    Join Date
    Oct 2014
    Location
    Sunshine Coast
    Posts
    74

    Default

    Quote Originally Posted by phild01 View Post
    Backblocking is easy and the boards won't move. Villaboard joins must be supported by either noggins or backblocking.
    hmm, i've not back blocked or used noggins as per the villaboard installation manual which says it's not mandatory. i've taped and filled the joints and there doesn't seem to be any movement. i will have to see how it goes as there's not opportunity to back block at this stage.

    the shower recess is pretty small with studs at 350. two walls are villaboarded horizontally with a joint at 350 high on one side and 1200 high on the other. i didn't want the joint to be inline with the mixer valve so i used the short board on that wall hence the 350.

    J

  8. #8
    Community Moderator phild01's Avatar
    Join Date
    Aug 2009
    Location
    Sydney, north
    Posts
    16,194

    Default

    Quote Originally Posted by johnnt View Post
    hmm, i've not back blocked or used noggins as per the villaboard installation manual which says it's not mandatory. i've taped and filled the joints and there doesn't seem to be any movement. i will have to see how it goes as there's not opportunity to back block at this stage.
    Been a while since I referred to their installation manual but I do remember it being in-line noggins for the boards join.
    refer note 2 page 9 of their recent publication.
    http://www.jameshardie.com.au/upload...20OCT%2014.pdf

    I wouldn't deviate from that recommendation.

  9. #9
    Member
    Join Date
    Oct 2014
    Location
    Sunshine Coast
    Posts
    74

    Default

    Quote Originally Posted by phild01 View Post
    Been a while since I referred to their installation manual but I do remember it being in-line noggins for the boards join.
    refer note 2 page 9 of their recent publication.
    http://www.jameshardie.com.au/upload...20OCT%2014.pdf

    I wouldn't deviate from that recommendation.
    Yes i saw that, and the combination of "although not mandatory" in note 2 and the recommendation for noggins only for "high impact" areas in note 3 suggested a low impact area so not needed.

    I guess it's too late now - i've taped the joins and also reinforced them during the WP with a membrane with built in bond breaker. It all feels very solid. Also studs are closer that than the 600max so hopefully should be ok.

    J

  10. #10
    Community Moderator phild01's Avatar
    Join Date
    Aug 2009
    Location
    Sydney, north
    Posts
    16,194

    Default

    10mm thick tiles with a cement based adhesive will hold it all quite well.

Similar Threads

  1. Replies: 38
    Last Post: 25th Jan 2017, 01:56 PM
  2. bathroom wall joints and bond breaker
    By inferno6688 in forum Waterproofing
    Replies: 6
    Last Post: 29th Nov 2016, 12:32 PM
  3. Bond Breaker tape from Gripset with Davco k10
    By zeroasylum in forum Waterproofing
    Replies: 11
    Last Post: 20th Oct 2016, 10:07 AM
  4. Davco K10 & Bond Breaker
    By johnstonfencing in forum Waterproofing
    Replies: 5
    Last Post: 23rd Oct 2015, 06:00 PM
  5. bond breaker rod
    By UNIQUO in forum Bathrooms
    Replies: 11
    Last Post: 6th Apr 2013, 12:32 AM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •